How many yards of dirt do I need?

Multiply length in feet by width in feet by depth in feet, then divide by 27. For depth in inches, divide by 12 first. A 1,000 square foot area at 6 inches deep is about 18.5 cubic yards. Then add 10 to 25 percent for settlement or compaction depending on how the material is placed.

How many cubic yards do I need?

Enter the area and the depth. The calculator returns loose cubic yards, an approximate tonnage and a compacted allowance.

0.0loose cubic yards
0.0order this many yards
0.0tons, approx

Minimum order is 20 cubic yards.

Coverage per cubic yard

How far 1 cubic yard spreads, at common depths. Figures are square feet of coverage per cubic yard, rounded. These apply to any bulk material sold by the cubic yard.

DepthOne cubic yard covers
1 inch324 square feet
2 inches162 square feet
3 inches108 square feet
4 inches81 square feet
6 inches54 square feet
12 inches27 square feet

How does the arithmetic work?

A cubic yard is 27 cubic feet: a block 3 feet by 3 feet by 3 feet. To work out what you need, multiply the length in feet by the width in feet by the depth in feet, then divide by 27. That is the whole calculation, and everything else on this page is about the allowance you add to the answer.

Depth is almost always given in inches, so divide the inches by 12 first. 4 inches is 0.333 feet. 6 inches is 0.5 feet. A 20 foot by 30 foot area at 4 inches deep works out at 20 times 30 times 0.333, which is 200 cubic feet, or about 7.4 cubic yards.

For weight, 1 cubic yard of aggregate, sand or dirt runs about 1.5 tons as a general guide. That is the figure we publish on our own tools page. Wet clay is heavier than dry topsoil, so treat it as a planning number rather than a scale reading, and use it for working out truck loads rather than for a weight ticket.

Why do I have to allow for settlement?

Loose material off a truck occupies more space than the same material once it has been spread, watered and walked on. How much more depends on what it is and how it is placed, but it is never zero. This is the single most common reason a job comes up short on the last load.

For topsoil going down to a finish level you care about, add about 10 percent and rake it slightly proud so it settles into the level rather than below it. For clay fill being placed and settled, 10 to 20 percent. For select fill being compacted in lifts to a specification, budget 20 to 25 percent, because the compacted volume will be meaningfully less than the loose volume you bought. That is the compaction doing its job.

Running short is worse than running over. A second trip to top up a job is a full trucking charge on a small quantity, which is the most expensive dirt you will ever buy. Trucking is roughly 90 percent of the cost of a load, and that cost does not scale down when the quantity does.

How do I handle awkward shapes?

Pools and ponds are what people get wrong most often. A pool is not a box. It has a shallow end, a deep end and a transition, so estimate it as an average depth across the whole footprint rather than using the shallow-end depth. For a typical residential pool that average often lands near 5 feet, which is a great deal more yardage than the 3 feet people picture. A 16 foot by 32 foot pool at an average 5 feet is about 95 cubic yards.

For circles, the area is pi times the radius squared. A 24 foot diameter circle has a 12 foot radius, so the area is about 452 square feet. At 6 inches deep that is 226 cubic feet, or about 8.4 cubic yards.

For a sloping yard, break it into sections with roughly even depth, work each one out separately and add them up. Measuring the deepest point and applying it across the whole area is the fastest way to over-order by double. If you genuinely cannot work it out, give us the dimensions and what you are doing and we will run it with you on the phone.

Worked examples

4 jobs we get asked to price constantly, with the arithmetic shown so you can check it against your own dimensions rather than taking our word for the answer.

New lawn, 1,500 square feet of topsoil at 4 inches

1,500 times 0.333 is 500 cubic feet. Divided by 27 that is 18.5 cubic yards. Add 10 percent for consolidation and order about 20 cubic yards, which lands exactly on our minimum order.

Raising a low back yard, 40 feet by 60 feet by 8 inches

40 times 60 times 0.667 is 1,600 cubic feet. Divided by 27 that is 59.3 cubic yards of clay fill. Add 15 percent for settlement and order about 68 cubic yards. If grass has to grow, budget a further 30 cubic yards of topsoil for a 4 inch cap over the same area.

Backfilling a 16 foot by 32 foot pool

Use an average depth across the footprint, not the shallow end. At an average 5 feet, 16 times 32 times 5 is 2,560 cubic feet, or about 95 cubic yards. The shell normally gets broken up first so water drains through rather than collecting, and the backfill goes in as common fill in lifts.

A 40 foot by 50 foot building pad raised 12 inches

40 times 50 times 1 is 2,000 cubic feet, or about 74 cubic yards in place. Select fill compacted in 6 to 8 inch lifts wants a 20 to 25 percent allowance, so order 89 to 93 cubic yards. Ordering the in-place figure is how pads run short on the last lift.

Where do I go from here?

Once you have a number, we need the delivery address to price it, because haul distance is the biggest single variable in what a cubic yard costs. The minimum order is 20 cubic yards. If your figure is close to the minimum, check the whole area you want covered before you call, because most people find a second low spot.

Bags, tons, wheelbarrows and pickups Yards per dump truck

Yardage questions

How do I calculate how much dirt I need?

Multiply the length in feet by the width in feet by the depth in feet, then divide by 27, because 1 cubic yard is 27 cubic feet. If your depth is in inches, divide it by 12 first. Then add 10 to 25 percent for settlement or compaction depending on how the material is being placed.

How many cubic feet are in a cubic yard?

27. A cubic yard is a block 3 feet by 3 feet by 3 feet, and 3 times 3 times 3 is 27. That single number is behind every conversion on this site, including the bagged soil arithmetic, where you divide 27 by the cubic feet printed on the bag.

How much does 1 cubic yard of dirt cover?

324 square feet at 1 inch deep, 108 square feet at 3 inches, 81 square feet at 4 inches, 54 square feet at 6 inches and 27 square feet at a full 12 inches. Divide 324 by the depth in inches to get the coverage for any depth.

How much extra should I order for compaction?

10 percent for topsoil going to a finish level, 10 to 20 percent for clay fill being placed and settled, and 20 to 25 percent for select fill compacted in lifts to a specification. The calculator applies your choice and shows both the loose volume and the volume to order.

How much dirt does it take to fill a swimming pool?

Estimate the average depth across the whole footprint rather than the shallow end. For a typical residential pool that average often lands near 5 feet. A 16 foot by 32 foot pool at an average 5 feet is about 95 cubic yards. Most residential pool fills land somewhere between 60 and 100 cubic yards.

What is the minimum I can order?

20 cubic yards. Below that the trucking cost swamps the material cost, because roughly 90 percent of what a load costs is the truck rather than the dirt. If your calculation comes out under 20 cubic yards, check the whole area you want covered before you call.

Order a load

Once you have a number, we need the delivery address to price it. Haul distance is the biggest single variable in what a yard costs.

Call us Get a dirt quote