Clean dirt, wholesale bulk pricing, 20 cubic yard minimum [email protected]
American Dirt Delivery (713) 547-5624
Materials

Clay fill, select fill and topsoil

3 materials cover almost every job that needs bulk dirt, and they are not interchangeable. Clay fill adds volume. Select fill carries load. Topsoil grows things. All 3 are sold by the cubic yard with a 20 cubic yard minimum, and none of them can be returned once the truck has tipped.

Which material do I need?

Short version. Use clay fill dirt to add volume: raising low ground, filling holes, backfilling a pool. Use select fill under anything that carries weight: a slab, a driveway, a patio, placed in 6 to 8 inch lifts and compacted. Use topsoil for the top 4 to 6 inches, where something has to grow. All 3 are sold by the cubic yard with a 20 cubic yard minimum.

The three materials side by side

The 3 materials side by side. Every figure in the weight row is a rule of thumb that moves with moisture content: the same cubic yard of clay weighs noticeably more after a wet week than it does in a dry August.

Clay fill dirtSelect fillTopsoil
What it isSubsoil below the topsoil layer, mostly clayA graded sand and fines blend chosen to compactThe thin organic top layer of the ground
Main jobAdding bulk volumeCarrying structural loadGrowing grass and plants
Compacts predictablyNo. Density depends on moisture on the dayYes. That is what you are paying forNo. It consolidates and loses volume
Will plants grow in itBarely. Almost no organic matterNo. It is a construction materialYes. That is the entire point
Typical placement depthIn lifts to whatever height you need6 to 8 inch lifts, compacted each lift4 to 6 inches lawn, 8 to 12 inches beds
Volume allowance to order10 to 20 percent over the calculation20 to 25 percent for a compacted padAbout 10 percent for consolidation
Relative cost per cubic yardCheapest of the 3Middle. You pay for the gradationDearest. It is the scarcest
Rough weight per cubic yardHeaviest. Wet clay more againSimilar to fill, slightly more granularLightest of the 3
Share of what we sellOver 80 percentMost of our Texas pad workThe finishing layer on most grading jobs

Four questions that settle it

Almost every material mistake we see comes from answering the wrong question. People start from what a material is called and work forwards. Start from what the ground has to do instead, and there are only 4 questions.

Am I holding something up?

If a slab, a driveway, a sidewalk, a patio or a retaining wall is going to sit on it, the answer is select fill, placed in 6 to 8 inch lifts and compacted. Clay fill under a structure is how you buy a foundation problem 5 years from now, because clay changes volume with its moisture content and concrete does not.

Am I just adding volume?

Raising a low yard, filling a hole, backfilling a decommissioned pool, building a berm or shaping a track. That is clay fill dirt, the cheapest material on this page and over 80 percent of what we sell. Pay for select fill here and you have spent extra on a property you are not using.

Does something have to grow in it?

Then topsoil, and only in the top layer. Topsoil is a finishing material, not a bulk one. Build the grade with fill and cap it with 4 to 6 inches of topsoil rather than trying to buy the whole 12 inch lift in the dearest material on the list.

Do I have a spec sheet?

If an engineer or a geotechnical report is attached to the job it will name a plasticity index ceiling, a gradation and a required compaction percentage against a Proctor test such as ASTM D698. Send us that before you order rather than after the inspection. If we cannot source to it, we will say so.

What happens if I order the wrong one?

You pay the trucking twice. That is the whole answer, and it is why this page exists. Roughly 90 percent of what a load of dirt costs is the truck rather than the dirt, so a wrong material is not a small correction. We do not accept returns on bulk material and we do not refund trucking after a delivery has been made, because the truck cost was spent the moment the wheels turned.

The 2 expensive mistakes run in opposite directions. Filling a 3 foot hole with topsoil means buying the dearest material on the list for a job the cheapest one does better, and then watching the ground sink for years as the organic content breaks down. Capping a new lawn with clay fill means buying material nothing will grow in, and then buying the topsoil you should have ordered in the first place.

The third mistake is subtler and more expensive. Using clay fill under a slab, a driveway or a patio because it was cheaper per yard works fine until the first full wet and dry cycle. Then the clay swells, the concrete follows it up, the clay shrinks and the concrete cracks. That correction is not a second dirt delivery, it is a concrete job.

Can I order more than one material on the same delivery?

Yes, and on a lot of jobs you should. The common combination is clay fill for the bulk of the lift and topsoil for the top 4 to 6 inches. Raising a 1,000 square foot area by 1 foot is about 37 cubic yards total, which splits roughly 25 yards of fill and 12 yards of topsoil.

Tell us the split when you order so we can work out the loads, because different materials generally come on different trucks and the sequencing matters. Fill goes down and gets shaped first. Topsoil arrives once the grade underneath it is right, not before, or you will be moving the topsoil twice.

The 20 cubic yard minimum applies to the order rather than to each material, so a 25 yard fill and 12 yard topsoil order is a single 37 yard order and it clears the minimum comfortably.

The three pages in full

Each material has its own page with the working properties, the placement depths, how it behaves across our markets and a worked yardage example.

Select fill being placed in lifts on a building pad

Select Fill Dirt

The spec-driven fill. Building pads, driveway subgrade, flatwork base and backfill against retaining walls. It compacts and it stays compacted.

Read the full page
Bulk topsoil spread over a prepared lawn grade

Topsoil Delivery

The growing layer. 4 to 6 inches over a prepared grade for lawn, 8 to 12 inches for beds. The dearest of the three, because there is least of it.

Read the full page

Fill dirt vs topsoil, head to head Work out my yardage

Choosing a material

Which material is cheapest?

Clay fill dirt, every time. It is the most abundant of the 3 and it needs the least processing. Topsoil is the dearest because there is genuinely less of it in the ground. It is a thin surface layer, and every cubic yard sold came off the top of somewhere else. Select fill sits between them, and the premium buys a gradation that compacts predictably.

Can I use topsoil as fill dirt?

You can put it in a hole and you should not. Topsoil has organic matter in it, organic matter breaks down, and material that breaks down loses volume. A hole filled with topsoil sinks and keeps sinking. It also costs considerably more per cubic yard than the fill dirt that belongs there.

Can I mix materials on one order?

Yes. The common split is clay fill for the lift and 4 to 6 inches of topsoil on top. Tell us the split when you order so we can work out the loads and the sequence, because the topsoil should arrive after the grade underneath it is right. The 20 cubic yard minimum applies to the order rather than to each material.

What if I am not sure which one I need?

Describe the job and the site rather than guessing. What you are building, what is going on top of it, how deep, and whether anything has to grow. That is a 2 minute conversation and it is a great deal cheaper than a wrong load, because bulk material is not returnable and the trucking is 90 percent of the cost.

Do you carry sand, road base or crushed concrete?

Our 3 published materials are clay fill dirt, select fill and topsoil. Other bulk products get asked for constantly, and what we can source varies by market and by haul distance. Name the product on your plans when you call and we will tell you straight whether we can get it to your address economically.

Still not sure which one?

Describe the job and the site and we will tell you which of the three suits it. That conversation costs nothing. A wrong load costs the trucking twice.

Call us Get a dirt quote